Commercial Building Case Study
Half-off the grid, California, US
Problem
A commercial building in California has constant high power requirements. The grid purchasing costs for them consists of energy charges and demand charges, and demand becomes a large part of their bill when they use a lot of power over a short period of time.
Since California has high solar insolation throughout the year, a grid tied renewable system integration would certainly help alleviate demand charge problems.
Solution
In this commercial building case study, inclusion of a battery energy storage system allows more contribution from solar PV into the mix, taking the commercial building practically half-off the grid. BESS integration also allows for demand response activities for the building like peak shaving, energy arbitrage amongst others.
Cost Saving Benefits
The overall project cost is US$616,350. The local electricity rate is US$0.17/kWh. Assuming 8 hours of sunshine per day, and with demand charge reduction of US$5000 per year, the annual savings will be US$152,431. This results in a payback period of just 4 years.
Daily Production | Demand Charge Reduction | Annual Revenue | Payback |
---|---|---|---|
2376 kWh | US$5000 | US$152,431 | ~4 years |
About The System
The system comprises of a 109 kWh BESS integrated with a 297-kW solar PV array and the grid. This setup will be able to support the buildings’ power demands during peak periods using the energy stored. Since the BESS is charged during off-peak period with either solar PV or the grid, significant amount of bill savings will be made.